Rail Coach Factory Kapurthala Fails To Deliver Any Vande Bharat Trains Against Target of 32
The Rail Coach Factory (RCF), Kapurthala, was supposed to deliver 32 Vande Bharat trains in 2022-23 but documents have revealed it did not deliver even a single one. This could affect the larger plan of running 75 Vande Bharat trains by August 2024.
The RCF in Kapurthala is the railway’s premier production unit and was tasked with delivering 32 Vande Bharat trains in 2022-23. Now, according to a new report, the factory has failed to deliver even a single train and has blamed the suppliers for not providing electrical components for the train sets. It also cited the spike in prices of raw materials which led to short fall in supply of parts like seats-berth, 60 KVA transformer, switch board cabinet, and shell components/ sub-assemblies.
As per the document assessed by PTI, the RCF said, “There was serious shortage of wheel supply from May to September 2022 leading to loss of production. Production of 87 coaches was lost on this account. The delay in supply of electrics by BHEL resulted in production loss of MEMU rakes. VB Trainset Coaches delayed as RCF did not get electrics from M/s Medha.”
Similar stories
Comments are closed.